Power interest grid: how to use it for a real decision

Updated 15 November 2026 · Huper.Technology

A power interest grid places each stakeholder by how much power they have over an outcome and how much interest they take in it, which sorts them into four groups: manage closely, keep satisfied, keep informed, monitor. It sorts a long list in minutes. What it cannot show is how that list changes once you act.

In short

  • Score power and interest for one decision, not for the organisation in general. A regulator can be high power on one decision and irrelevant to the next.
  • Write the evidence next to every score. A score without a reason is a guess with a number on it.
  • Interest is the axis that moves fastest. An announcement can drag an unengaged group into the top half of the grid within a day.
  • Low-power groups borrow power through the press, politicians and regulators. Draw those links, or the grid will tell you to ignore the group that starts the story.

What is a power interest grid?

It is a two-by-two chart. The vertical axis is power: how far a stakeholder can stop, delay, change or publicly damage what you plan to do. The horizontal axis is interest: how much they care about it and how closely they will follow it. Each stakeholder gets a dot, and the quadrant the dot lands in suggests a default way to engage them.

The idea is usually credited to Aubrey Mendelow, whose 1981 paper on environmental scanning argued that how closely an organisation watches each stakeholder should depend on that stakeholder's power. The four-box version most teams use today spread later through strategy teaching, project management and public-sector guidance. It is one of the three views covered in our stakeholder mapping guide; this page goes deeper on the grid alone.

What do the four quadrants mean?

Each quadrant sets a default level of engagement. Treat it as a starting point that the team can overrule with a reason.

QuadrantDefault treatmentWhat that looks like in practice
High power, high interestManage closelyInvolve before the decision is final. Brief in person. Give them a named contact and a route to raise concerns early.
High power, low interestKeep satisfiedBrief them before they hear it elsewhere. Keep it short. Watch for anything that would raise their interest.
Low power, high interestKeep informedExplain what is changing, why, and what support is on offer. Listen: this is where early warning signs show up.
Low power, low interestMonitorGeneral communication only. Recheck after the announcement.

The labels differ between sources. The UK Government Analysis Function, for example, calls the low-power, high-interest box "consult with" and the low-low box "keep informed". The logic is the same everywhere: effort follows power, and listening follows interest.

How do you build one for a decision?

  1. Write the decision down in one sentence. "We will close the Halden route on 1 March" scores very differently from "we are reviewing regional routes". The grid belongs to a decision, not to the organisation.
  2. List stakeholders as named actors. "Government" is not a stakeholder. The transport ministry, the regional council and the local member of parliament are three, and they will sit in different boxes.
  3. Agree what power means for this decision. Can they stop it, delay it, fine you, change its terms, or turn it into a news story? Write the scale before anyone scores.
  4. Score as a group, with evidence. Each score gets a reason: a statutory role, a contract, a past campaign, a public statement. Where people disagree, note why. The disagreement often tells you more than the score.
  5. Plot, then assign an owner and an action to every dot. A grid with no owners is a picture. A grid with owners is a plan. To record the scores, owners and actions in one place, use our stakeholder analysis template.

How should you score power and interest?

Use a 1–5 scale for each and define the ends before you start. These definitions work for most decisions with public exposure:

ScorePower: what can they do to the decision?Interest: how closely will they follow it?
5Stop or reverse it (approval, veto, licence, court order)It changes their income, job, service or mandate directly
4Delay it, fine you, or force a change in its termsIt is a priority issue for them this year
3Raise its cost: withdraw support, take business elsewhere, mobilise othersThey will notice and form a view
2Shape how it is reported or perceivedThey might notice if someone points it out
1No meaningful influence on this decisionIt does not affect them

Score interest as it will be the day after the announcement, not as it is today. Most stakeholders have low interest in a decision they have not heard about.

A worked example

The example is fictional. Harlow Air, a mid-sized regional airline, plans to end its only service to Halden, a small city, because the route loses money. The team drew this grid before the announcement.

StakeholderPowerInterestQuadrantReason
Pilots' union45Manage closelyBase closure affects crew contracts; can delay through consultation rules
Aviation regulator42Keep satisfiedSlot and licence matters; a route exit is routine for them
Halden regional council34Keep informedPart-funds the airport; no say over the airline's network
Local member of parliament32MonitorNo formal role; has not raised air links before
Halden business association24Keep informedMembers use the route weekly
Regional newspaper22MonitorCovers the airport occasionally

On this grid, only the union needs close handling. The council and businesses get a letter. The MP and the paper get nothing. That plan is defensible on paper, and it is the kind of plan that goes wrong in public.

Why do stakeholders change quadrant after you announce?

Because the announcement itself changes interest, and alliances change power. A static grid scores each group alone, at one moment. After a public decision, groups react to each other.

StakeholderBeforeA week afterWhat moved it
Halden business associationKeep informedManage closelyIts letter to the paper became the front page; it now speaks for "the city"
Regional newspaperMonitorKeep informed, risingA local-impact story with a clear villain and named victims
Local member of parliamentMonitorManage closelyConstituents and the paper made it their issue; asks a question in parliament
Aviation regulatorKeep satisfiedManage closelyFielding political questions about regional connectivity

Nothing about the business association's formal power changed. It borrowed power from the paper, and the paper lent it on to the MP, who passed the pressure to the regulator. The group the grid said to keep informed became the start of the chain. Grids miss this because they have no way to draw it.

Two fixes help. First, score interest for the day after, as above. Second, draw a relationship layer on top of the grid: who reads whom, who funds whom, who follows whose lead. The stakeholder mapping guide covers relationship maps in more detail.

What mistakes make the grid misleading?

When should you use the salience model instead?

Use it when the grid puts too many groups in the top-right box and you need to decide whose claim to act on first. Mitchell, Agle and Wood's salience model adds legitimacy and urgency to power, so a small group with an urgent, widely accepted grievance rises above a powerful group with a weak claim. Many teams use the grid to sort the full list, then the salience model on the top half.

Testing the grid before you act

The weak point in any power interest grid is the step from "where they sit now" to "where they will sit once this is public". That step is a forecast, and it is usually made by the same people who made the decision. The Harlow Air team did not get the scores wrong. They had no way to see the chain from the business association to the regulator before it ran.

Isaiah is built for that step. You bring the decision and the documents that frame it. Isaiah builds the stakeholder field from your material and fresh research, simulates those stakeholders reacting to the announcement and to each other in simulated public discourse, and tests alternative moves, such as briefing the council first or announcing a replacement service with the closure. The board-ready report shows which groups moved, which coalitions formed and which moves backfired, with each finding traced to quotes from named simulated stakeholders. The simulation stays open so you can question any of them.

It is a stress-test, not a forecast, and simulated stakeholders are not survey respondents. It gives your second grid something other than the drafting team's judgement to stand on.

Frequently asked questions

What is a power interest grid?

A two-by-two chart that places each stakeholder by how much power they have over an outcome and how much interest they take in it. The four quadrants suggest how to engage each group: manage closely, keep satisfied, keep informed, or monitor.

What are the four quadrants of the power interest grid?

High power and high interest: manage closely. High power and low interest: keep satisfied. Low power and high interest: keep informed (some guidance says consult). Low power and low interest: monitor. The labels vary between sources; the logic is the same.

Who created the power interest grid?

It is usually credited to Aubrey Mendelow, whose 1981 paper on environmental scanning linked how an organisation watches each stakeholder to that stakeholder's power. The grid in its familiar four-quadrant form spread later through strategy, project management and public-sector guidance.

What is the difference between the power interest grid and the salience model?

The grid scores two things, power and interest, and is quick to fill in. The salience model of Mitchell, Agle and Wood scores power, legitimacy and urgency, and is better for deciding whose claim to act on first when the grid puts too many groups in the top-right box.

Have a decision coming up?

Tell us what it is. We will set up a private stress-test on it and show you how the stakeholder field reacts before anything goes public.

Request a demo

Related

Sources

  1. Mendelow, A. L. (1981). Environmental Scanning: The Impact of the Stakeholder Concept. ICIS 1981 Proceedings, Paper 20. aisel.aisnet.org/icis1981/20 (checked 15 November 2026)
  2. Government Analysis Function (UK). Stakeholder mapping. analysisfunction.civilservice.gov.uk/policy-store/stakeholder-mapping (checked 15 November 2026)
  3. Mitchell, R. K., Agle, B. R., & Wood, D. J. (1997). Toward a Theory of Stakeholder Identification and Salience: Defining the Principle of Who and What Really Counts. Academy of Management Review, 22(4), 853–886. doi.org/10.2307/259247 (checked 15 November 2026)